Practice Question: Estimating Excavation Duration based on Equipment Productivity

NCEES Civil PE Specification Estimating Quantities and Costs: Work measurement and productivity


Problem

A grade beam with dimensions 3 feet in width and 4 feet in depth needs to be constructed along the outer edge of a building, as illustrated in the accompanying figure. The trench dug for the grade beam should have side slopes of 1V:1H. The excavation process will be carried out using a track hoe with a productivity rate of 12 cubic yards per hour.

Assuming an 8-hour workday, select the minimum number of days required to finish the excavation task. 

Ignore any savings associated with excavations corners. 

     PLAN

Select an Answer: