NCEES Civil PE Specification Project Planning and Scheduling: Project schedule analysis
Problem
While conducting project controls at a specific project stage, the project manager calculates the following values.
- Budgeted Cost of Work Scheduled (BCWS) = $580,000
- Actual Cost of Work Performed (ACWP) = $540,000
- Budgeted Cost of Work Performed (BCWP) = $620,000
Which of the following statements is true?
Select an Answer: