Practice Question: Net Excavation for a Foundation Plan

NCEES Civil PE Specification VIII.A.: Excavation and embankment


Problem

You are responsible for placement of 8 spread foundations required to support a new structure. Each foundation is composed of a square footing and pier as shown in the typical elevation. The project geotechnical report states that 3 feet of over-excavation and compaction is required below and around each footing. Based on typical footing dimensions shown, determine the total net excavation required for all foundations in cubic yards.

Select an Answer: