NCEES Civil PE Specification Project Planning and Scheduling: Activity time analysis
Problem
The given figure displays a node diagram representing project activities, with each duration presented in weeks. All relationships between activities are "finish to start." What is the free float, in weeks, for activity D?
Select an Answer: