Practice Question: Cost of Hauling for Loose Soil

NCEES Civil PE Specification Project Planning: Cost estimating


Problem

You are planning construction for a hip new multi-level apartment building. Part of the construction effort will require excavating an existing flat lot and hauling away spoils to a local landfill. You have contracted with a subcontractor that will provide hauling services at a flat fee of $300 per haul; trucks used for each haul have a maximum allowable volume of 14 cubic yards. Given dimensions shown in the figure and a swell factor of 0.2, determine the total cost of hauling all required excavation. 

Assume no over-excavation beyond building dimensions is required.

Project Planning: Cost estimating

Select an Answer: