Practice Question: Determining Early Start Time for Activity in a Project

NCEES Civil PE Specification Project Planning and Scheduling: Activity time analysis


Problem

The following figure illustrates an activity-on-arrow network for a project, with numbers adjacent to arrow indicating activity durations in weeks. Assuming the project start date is week 0, and using end-of-week calculations for starts and finishes, what is the early start date (in weeks) for activity I?

(Number inside the nodes represents activity level)

Select an Answer: