NCEES Civil PE Specification Project Planning and Scheduling: Activity time analysis
Problem
The following figure illustrates an activity-on-arrow network for a project, with numbers adjacent to arrow indicating activity durations in weeks. Assuming the project start date is week 0, and using end-of-week calculations for starts and finishes, what is the early start date (in weeks) for activity I?
(Number inside the nodes represents activity level)
Select an Answer: